Tracklaying underway on METRONET’s Airport Line - Public Transport Authority of Western Australia
Menu
  1. About us
  2. Our services
  3. Our system
  4. Projects
    1. Current projects
    2. Completed projects
  5. Careers
  6. News

/ Categories: PTA News

Tracklaying underway on METRONET’s Airport Line

  • One kilometre of track for Forrestfield-Airport Link project now in place
  • Heralds new stage of works and an important step towards completion of the project
  • 2,400 tonnes of Australian-manufactured steel to be used to build the track
  • Tracklaying and rail infrastructure works to support more than 100 additional jobs
  • Seven METRONET projects underway in 2020, supporting jobs and local businesses   

The transformational METRONET Forrestfield-Airport Link project has reached another major milestone, with tracklaying in the eight-kilometre tunnels now underway.

The first kilometre of track for the $1.86 billion METRONET project has been laid near Redcliffe Station, following the final breakthrough near Bayswater and completion of tunnelling in April.

Australian company Martinus Rail - under contract to Salini Impregilo-NRW Joint Venture - will use more than 2,400 tonnes of Australian-manufactured steel in the tracklaying process, with around 40 kilometres of rail needed to form the track in each tunnel, tie-ins at Bayswater and stowage at High Wycombe.

The rail started out as 27.5 metre pieces of steel before being flash-butt welded into giant 220 metre strings. Multiple teams work simultaneously to weld lengths of rail, transport and precisely lay the rail and sleepers to form the skeleton track in the tunnels, then pour the concrete that finishes the slab track.

Work is also underway to prepare for the installation of the overhead line equipment and the complex systems for communications and signalling. The tracklaying and rail infrastructure processes will support more than 100 jobs.

The Forrestfield-Airport Link will be named the Airport Line when it becomes operational, and will provide a 20 minutes' rail link between the Perth central business district and the eastern suburbs, with new stations at Redcliffe, Airport Central and High Wycombe.

Trains are scheduled to start running on the Airport Line in late 2021.

Previous Article Artists sought for high-profile Cockburn tower artwork
Next Article Promoting safety on Transperth network during Rail Safety Week
Print

Search news

Archive


PTA acknowledges the traditional custodians throughout Western Australia and their continuing connection to the land, waters and community.
We pay our respects to all members of the Aboriginal communities and to Elders past, present and emerging; and commit to building a brighter future together.

Aboriginal and Torres Strait Islander people are advised that this site may contain images or names of people who are deceased.

Copyright Disclaimer Terms Of Use Privacy Statement Webmail Copyright 2018 Public Transport Authority of Western Australia
Back To Top