During the Armadale and Thornlie Line shutdown the PTA will be undertaking major maintenance between Kenwick and Sherwood stations, as this section of rail is some of the oldest on the PTA network.
The work will include the renewal of 15kms of track, 25 pedestrian crossings and 10 level crossings, and improving and installing new drainage systems. There will also be upgrades to the overhead lines, communications, and signals facilities to connect to works being completed on METRONET’s Victoria Park-Canning Level Crossing Removal and Byford Rail Extension Projects.
For out-of-hours work updates please visit the METRONET website.