Supporting Our Community

Explanation of Major Capital Expenditure Variations 2011-12

(a) Budgeted estimates and actual results for 2011-12

 

Budget
$000

Actual
$000

Variation
$000

Comments

Grain Freight Re-sleepering Project

79,634

32,945

46,689

Project scheduling

Business Support Upgrades

7,569

890

6,679

Projects deferred

Bus Priority Projects

8,000

2,711

5,289

Project scheduling

Disability Access for Intermediate Minor Stations & Track Works

7,483

4,584

2,899

Project scheduling

Maddington Station Upgrade

2,599

89

2,510

Project scheduling

Track Recording System

2,250

4

2,246

Project cancelled

Warnbro Bus Rail Interchange

2,741

1,032

1,709

Project scheduling

Network & Infrastructure Maintenance Depot

2,632

1,143

1,489

Project scheduling

Power Supply Continuity Program

1,287

-

1,287

Project scheduling

Security Fire Protection

1,412

141

1,271

Project scheduling

Goongoonup (East Perth) Rail Bridge

2,079

3,297

(1,218)

Project scheduling

Escalator and Lift Upgrade

584

1,835

(1,251)

Project scheduling

Concrete Re-sleepering Project

5,513

7,488

(1,975)

Project scheduling

Extension of the Northern Suburbs Railway to Butler

46,498

55,415

(8,917)

Project scheduling

Bus Replacement Program

29,958

41,069

(11,111)

Project scheduling

Perth City Link

68,937

107,016

(38,079)

Project scheduling

Others

76,680

86,322

(9,642)

Project scheduling

         

Grand Total

345,856

345,981

(125)

 

(b) Major Works in progress and completed



Description of Work

2011-12
Estimated Total Cost
$000


Estimated Cost to Complete
$000


Total Cost of Project - Actual
$000


Expected Year of Completion
$000

Perth City Link

609,269

467,332

141,937

2015-16

Bus Replacement Program

431,369

389,835

41,534

2020-21

Extension of the Northern Suburbs Railway to Butler

250,230

177,630

72,600

2014-15

Disability Access for Intermediate Minor Stations & Track Works

33,304

25,658

7,646

2016-17

Bus Priority Projects

25,590

19,402

6,188

2015-16

Better Transport System (3000 parking bays)

50,022

4,944

45,078

2012-13

Concrete Re-sleepering Projects

60,641

(355)

60,996

2012-13

Bus Acquisition Program

406,375

120

406,255

2011-12

Grain Freight Re-sleepering Project

171,420

114,291

57,129

2013-14