EFFICIENCY INDICATORS
Services
Performance measures have been developed for each
mode of transport to measure the cost efficiency of
the services delivered.
Metropolitan and regional passenger
services
Provision of customer focussed, safe and cost effective
passenger transport to the metropolitan area and
regional towns.
Average cost per passenger kilometre
The cost per passenger kilometre measures the cost
efficiency of providing passenger services, expressed as
the cost of carrying one passenger one kilometre.
Passenger kilometres are currently based on the zonal
distribution of passenger trips and an assumed average
trip length for each zone. Ideally, the average passenger
trip length on each mode should be determined more
accurately, through a survey, and multiplied by the
number of trips on that mode to calculate passenger
kilometres.
Transperth Train Operations
Following the expansion of train services, passenger
kilometres increased by 6.0% in 2004/05. However, the
total cost of providing train services increased by
34.5% largely due to a significant increase in capital
charges associated with the long term investment in
the extension of the railway line both in the Northern
and Southern suburbs. Furthermore, as a result of the
service expansion, operating costs rose by 19.4%. |
Transperth
Bus Operations
The variance is due to an increase in total costs of
6.1% while passenger kilometres increased by only
2.4%.
The increase in total costs was the result of both
higher capital charges (increase of 11%) following the
acquisition of new buses, and higher operating costs
(increase of 4.7%).The increase in the operating costs
was as a result of expenditure on security issues,
ticketing system maintenance, higher insurance and
vehicle licensing costs as well as bus stop and
infrastructure maintenance.
Transperth Ferry Operations
The actual 2004/05 cost per passenger kilometre is
significantly higher than the target for 2004/05 as a
result of the target being based on an underestimated
budget which did not reflect the total cost of operating
the ferry service.
|