Commissioning of the new Thornlie Line and
driver
training were due to begin in mid-July 2005 for the
official opening of Thornlie Station on 7 August 2005
and commencement of passenger services the
following day.
A contract for the supply and maintenance
of 93 new
railcars was let to EDI Rail Bombardier Transportation
in May 2002.The new railcars are being manufactured
in Maryborough, Queensland and fitted out and
commissioned at the PTA’s Nowergup Depot in WA.
The first
54 new railcars had been accepted for service
by the end of the year. The remaining railcars will be
progressively delivered, tested, commissioned and
accepted for service by June 2006.
In a significant boost for
passenger security, the
centralised TV monitoring of Transperth stations began
in 2004/05 (see Passenger Safety below).
Replacement of life-expired
timber sleepers with
concrete sleepers on the Fremantle Line was
completed during the year and was about to begin on
the Armadale Line, with the Midland Line to follow.
Concrete sleepers provide a much more stable track
requiring less maintenance.
The recruitment of additional staff
in train operations
continued to ensure safe and reliable train services.
The service reliability target for Transperth train
services requires trains to arrive within three minutes
of the scheduled time. In 2003/04, an industrial dispute
resulted in the on-time arrival rate falling to 89.3 per
cent compared with 96.4 per cent the previous year.
This deterioration in service was reversed in 2004/05
when 94.4 per cent of services met the reliability
target.
Cost of the Service
The total cost of providing
train services recorded a
significant increase due largely to an increase in capital
charges related to New MetroRail. Total expenditure,
which amounted to $143.7 million in 2003/04,
increased by 32.2 per cent to $190.2 million in
2004/05. Operating cost (which excludes capital
charges) rose by 19.3 per cent from $78.7 million to
$93.9 million, including the expenditure on the
expanded service to Clarkson.
Patronage
In 2002/03 and 2003/04, patronage
on Transperth train
services had stabilised at around 18.8 million farepaying
boardings and 31.1 million total boardings. In
2004/05, train patronage recorded a significant
improvement following the extension of the train
network to Clarkson, the opening of the station at
Greenwood and the introduction of additional
rollingstock. Fare-paying boardings rose 6.3 per cent
from 18.847 million to 20.038 million and total
boardings increased by 4.9 per cent from 31.115
million to 32.652 million. |
Since
2000/01, train patronage has recorded increases
of 18.4 per cent in fare-paying boardings and 12.1 per
cent in total boardings.
While train patronage recorded this significant
increase, the expansion of services resulted in train
service kilometres increasing at a higher rate, 7.0 per
cent. Consequently, on a per service kilometre basis,
fare-paying boardings on train services fell by 0.6 per
cent from 2.813 in 2003/04 to 2.796 in 2004/05 and
total boardings by 1.9 per cent from 4.644 to 4.556.
Customer Satisfaction
The Passenger Satisfaction Monitor 2005
showed that
a high proportion of users were satisfied with the train
system overall. The small reduction experienced in
2004 when the satisfaction rate fell to 90 per cent was
reversed and a rate of 92 per cent was achieved in 2005.
|