NEW METRORAIL PROGRESS

Work continued on construction of the Southern Suburbs Railway, the centrepiece of the New MetroRail project. Construction of the railway was nearly complete at year’s end, and testing, commissioning and handover were underway.

The Southern Suburbs Railway comprises 72 route kilometres of double-track railway between Perth and Mandurah, eleven stations, 770 metres of twin tunnels under the Perth CBD, 18 bridges and structures, significant road and civil works, a 25kv electrical traction power overhead wiring system, signalling and communications and two electrical power feeder stations.

The New MetroRail project also involves the design, construction and maintenance of 93 new B-series electric railcars, view image the last of which was delivered in July 2006 and all of which are operating successfully on the Joondalup Line between Perth and Clarkson and are stored and maintained at a new depot located at Nowergup. view image

Total expenditure in 2006/07 was $276.21 million, bringing total expenditure on the New MetroRail Project to $1,559.6 million (98.1% of the total budget).

The target date for commencement of services on the Southern Suburbs Railway was 29 July 2007. There were delays in completion of a number of critical areas of the infrastructure and the interface works between major contracts. There were a number of claims from contractors for extensions of time, delays and extra cost. A number of these claims are being disputed through the courts.

In May 2007, it was announced that the 29 July 2007 completion date for the Southern Suburbs Railway was unachievable. At year’s end, a completion date had not been determined even though the indication was that the works would be substantially completed by October.

The major highlights of the New MetroRail project during 2006/07 were: