Explanation of Major Capital Expenditure Variations 2008/09

( a ) Budgeted estimates and actual results for 2008/09

 

Budget
$000

Actual
$000

Variation
$000

Comments

Metropolitan & Regional Passenger Services

       

Train Control Upgrade

-

3,641

3,641

Project scheduling

Beckenham Bus Depot Acquisition

3,330

6,740

3,410

Project scheduling

Bus Acquisition Program

36,612

39,226

2,614

Project scheduling

Replacement Cash Ticket Vending Machines (TVM's) at Railway Stations

2,269

4,193

1,924

Project scheduling

Public Transport Centre UPS Project

-

1,443

1,443

Project scheduling

Accessible Public Transport Upgrade Program

666

2,075

1,409

Project scheduling

Geraldton Bus Depot Acquisition

-

1,000

1,000

Project scheduling

PTA Facilities Refurbishment

1,500

2,422

922

Project scheduling

Concrete Resleepering Projects

10,836

11,453

617

Project scheduling

Welshpool Depot Development

-

565

565

Project scheduling

Better Transport System (3000 parking bays)

6,222

3,713

(2,509)

Project scheduling

Victoria Park Station

3,484

951

(2,533)

Project scheduling

Karrinyup Depot Refurbishment

5,000

2,455

(2,545)

Project scheduling

Bus Acquisition Program - RPT Fleet

6,700

-

(6,700)

Project scheduling

North Greenbushes Project

13,150

-

(13,150)

Project scheduling

Others

120,884

107,497

(13,387)

Project scheduling

Corporate

       

Kewdale Freight Complex Redevelopment

8,092

5,111

(2,981)

Project Scheduling

New MetroRail

-

69,970

69,970

Revised project cost

GRAND TOTAL

218,745

262,455

43,710

 

( b ) Major works in progress and completed

Description of work

Estimated Total Cost 2008/09 $000

Estimated Cost to Complete $000

Total cost of project Actual $000

Expected year of Completion

Comment

Bus Acquisition Program

404,481

76,670

 

2010/11

 

Better Transport System (3000 parking bays)

51,022

45,861

 

2012/13

Better Transport System costs incorporate government commitment to an additional 1500 bays

45 New EMU Railcars (15 sets)

160,000

43,861

 

2010/11

 

Regional Bus Acquisition

52,434

40,290

 

2018/19

 

Disability Access for Intermediate Minor Stations & Track Works - Stage 2

33,304

33,058

 

2016/17

 

Concrete Resleepering Projects

61,741

27,271

 

2012/13

 

Bus Priority Projects

26,330

24,204

 

2013/14

 

Kelmscott Station - Upgrade

12,872

 

12,976

   

Wheel Lathe Acquisition and Facility

4,894

 

4,926

   

Train Control Upgrade

16,897

 

16,897

   

Public Transport Centre UPS Project

1,300

 

1,443

   

Beckenham Bus Depot Acquisition

6,730

 

6,740

   

Welshpool Depot Development

5,661

 

5,324