April 2017 update
News Articles | 10 April 2017

April 2017 update

Works are underway to ensure key support infrastructure is in place and ready for the first TBM to begin tunnelling in July this year. However, before the TBMs can start digging the 8kms of tunnels, they each need a name.

January 2017 update
News Articles | 18 January 2017

January 2017 update

With the arrival of the tunnel boring machines and all four major construction sites becoming operational in 2017, this year will be our busiest yet.

2016 end of year update
News Articles | 16 December 2016

2016 end of year update

This year has seen the project shift into construction phase, with SI-NRW awarded the major design and construct contract in April and starting construction works in November.

October 2016 update
News Articles | 31 October 2016

October 2016 update

The development application for Early Works at Forrestfield was approved this month and as a result preparation for the construction of key infrastructure has now started.

September 2016 update
News Articles | 7 October 2016

September 2016 update

Works are now underway to establish the construction site at Forrestfield. This is the first step in preparing for the arrival of the tunnel boring machines (TBMs) mid next year.

August 2016 update
News Articles | 5 September 2016

August 2016 update

There has been a hive of activity across the entire project footprint this month with site investigations conducted, final designs being progressed and PTA’s forward works continuing as planned.

July 2016 update
News Articles | 5 August 2016

July 2016 update

This month PTA and SI-NRW have been busy progressing designs for the upcoming construction works

 

 

 

 

 

June 2016 update
News Articles | 13 July 2016

June 2016 update

Forward works in the Belmont and Forrestfield Station Community Zones progressing well

May 2016 update
News Articles | 27 May 2016

May 2016 update

Central Avenue road connection works: progress update and temporary changes to road conditions

Major contract awarded
News Articles | 28 April 2016

Major contract awarded

The major contract for the Forrestfield-Airport Link project has been awarded to Salini Impregilo - NRW Joint Venture

RSS
First678910111315


Media enquiries about the Forrestfield-Airport Link can be directed to the Public Transport Authority:
Media line: (08) 9326 2526
Email: media@pta.wa.gov.au
Please note emails are monitored Monday to Friday, 9am to 5pm AWST.

Media enquiries from students must be sent from school or university email accounts.