July 2019 update
News Articles | 11 July 2019

July 2019 update

This week the team celebrated our second 130m-long tunnel boring machine (TBM) arriving at Redcliffe Station. TBM Sandy broke through into the underground station box at 9:30am on Saturday, July 6.

Skybridge construction takes to the skies in latest milestone
Media Statements | 2 July 2019

Skybridge construction takes to the skies in latest milestone

Premier Mark McGowan and Transport Minister Rita Saffioti today visisted the developing Skybridge at Airport Central Station.

June 2019 update
News Articles | 7 June 2019

June 2019 update

Tunnel boring machine (TBM) Grace arrived at Redcliffe Station last month, breaking through the one-metre-thick eastern station box wall to a cheering crowd of excited team members.

Forrestfield-Airport Link tunnelling pauses following slurry spill
Media Statements | 14 May 2019

Forrestfield-Airport Link tunnelling pauses following slurry spill

Tunnelling operations have paused on the Forrestfield-Airport Link after a section of piping servicing one of the tunnel boring machines (TBM) dislodged in Tunnel Two, causing a slurry spill.

Record METRONET budget as TBM Grace reaches Redcliffe Station
Media Statements | 13 May 2019

Record METRONET budget as TBM Grace reaches Redcliffe Station

Premier Mark McGowan and Transport Minister Rita Saffioti today welcomed the arrival of TBM Grace to the Redcliffe Station construction site, as the State Government highlighted the significant investment in METRONET as part of this week's State Budget.